P Prentice
Arvada, CO

Arvada is building
data centers

Arvada has 100 MW of data centers across 1 sites. That is a lot of work for the trades, and there are not enough workers nearby to do it.

1 sites |100 MW still to build |192 workers at peak
Running now
0 MW
Still to build
100 MW
Total workers on site at peak
192
Building sites
1
Arvada data centers: running now vs. still to build
Running now: 0 MW Still to build: 100 MW Total: 100 MW
The bottom line

Worth training up for in Colorado?

YES means the data centers will need more of that trade than Colorado can spare — so they pay well, pay to train, and run overtime. NO means there are already plenty.

NO
Ironworkers
Plenty already — about 235 to spare
NO
Data center technicians
Enough already — 15 steady jobs once they open
NO
Electricians
Plenty already — about 4,231 to spare
NO
Pipefitters
Plenty already — about 2,471 to spare
NO
HVAC/R technicians
Plenty already — about 2,206 to spare
NO
Sheet metal workers
Plenty already — about 399 to spare
NO
Carpenters
Plenty already — about 3,427 to spare
NO
Welders
Plenty already — about 1,103 to spare
NO
Network/low-voltage technicians
Plenty already — about 813 to spare
NO
Plumbers
Plenty already — about 2,483 to spare

"Short" means the data centers need more of that trade at the busiest point than the area has free to take on new work. Most workers stay on their regular jobs; only about 1 in 4 are free for big new projects like these.

Enough workers?

Will Colorado have enough workers?

At the busiest point of the build. Bars to the left mean a shortage (good if you are in that trade). Bars to the right mean workers to spare.

just enough SHORT TO SPARE Ironworkers 235 spare Sheet metal workers 399 spare Network/low-voltage technicians 813 spare Welders 1,103 spare HVAC/R technicians 2,206 spare Pipefitters 2,471 spare Plumbers 2,483 spare Carpenters 3,427 spare Electricians 4,231 spare
The short version

What this means for workers near Arvada

Arvada, CO has about 100 MW of AI data centers across 1 site, with 100 MW still to build. The builders here include DOE / NREL (seeking private developer).

At the busiest point, about 192 skilled workers will be on these sites at once, across all the trades. Many drive in from nearby towns, but the work starts here — and it is not split evenly, so some trades are short and some are not.

Worth training up for? The work near Arvada is steady, but the area has enough workers for most trades. Here is the read by trade.

Ironworkers — probably not, just for this. The data centers need about 27 ironworkers, and Colorado already has about 262 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

Electricians — probably not, just for this. The data centers need about 54 electricians, and Colorado already has about 4,285 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

Pipefitters — probably not, just for this. The data centers need about 21 pipefitters, and Colorado already has about 2,492 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

HVAC/R technicians — probably not, just for this. The data centers need about 12 hvac/r technicians, and Colorado already has about 2,218 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

Sheet metal workers — probably not, just for this. The data centers need about 6 sheet metal workers, and Colorado already has about 405 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

Carpenters — probably not, just for this. The data centers need about 33 carpenters, and Colorado already has about 3,460 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

These are some of the best-paying jobs you can get without a four-year degree. When a trade is short, builders run overtime and pay to train, and experienced workers can clear $100,000 a year, with health care and a pension through the union. It is the same across the country: builders cannot find enough skilled workers. The U.S. needs about 140,000 more trade workers by 2030 to build all the data centers, and most builders say hiring is their hardest problem. Microsoft's president has called the shortage of electricians the biggest thing slowing data centers down.

You sign up and get your license through Colorado. The Colorado trade pages show you how to start. Sources: a national survey of data-center building plans, plus U.S. jobs and pay data.

Every trade

Every trade, by the numbers

Is there a shortage of each trade for the data centers in the Arvada area?
Trade Needed at peak Free to take it on Short or extra New data-center jobs Train up?
Electricians 54 4,285 4,231 spare 4 NO
Carpenters 33 3,460 3,427 spare NO
Ironworkers 27 262 235 spare NO
Pipefitters 21 2,492 2,471 spare NO
Welders 15 1,118 1,103 spare NO
HVAC/R technicians 12 2,218 2,206 spare 2 NO
Network/low-voltage technicians 12 825 813 spare 1 NO
Plumbers 9 2,492 2,483 spare NO
Data center technicians 312 297 spare 15 NO
Sheet metal workers 6 405 399 spare NO
Elevator mechanics 3 95

"Needed at peak" is the most of that trade working across all the building at the busiest time. "Free to take it on" is how many local workers could move to data-center jobs — about 1 in 4 of the trade; the rest keep their regular jobs. "Short or extra" is the gap. "New data-center jobs" are permanent jobs that stay once a data center opens. "Train up?" is YES when the work needs more than the area can spare (so they pay well and pay to train), NO when there are plenty already. Elevator mechanics are left out of the verdict because their work depends on the building's design.