P Prentice
Kansas City (Northland), MO

Kansas City (Northland) is building
data centers

Kansas City (Northland) has 700 MW of data centers across 2 sites. That is a lot of work for the trades, and there are not enough workers nearby to do it.

2 sites |700 MW still to build |1,344 workers at peak
Running now
0 MW
Still to build
700 MW
Total workers on site at peak
1,344
Building sites
2
Kansas City (Northland) data centers: running now vs. still to build
Running now: 0 MW Still to build: 700 MW Total: 700 MW
The bottom line

Worth training up for in Missouri?

YES means the data centers will need more of that trade than Missouri can spare — so they pay well, pay to train, and run overtime. NO means there are already plenty.

YES
Ironworkers
Tight — needs almost all the area can spare
CLOSE
Data center technicians
Some steady jobs — 103 steady jobs once they open
NO
Electricians
Plenty already — about 2,787 to spare
NO
Network/low-voltage technicians
Plenty already — about 716 to spare
NO
Pipefitters
Plenty already — about 1,828 to spare
NO
Carpenters
Plenty already — about 3,867 to spare
NO
HVAC/R technicians
Plenty already — about 2,006 to spare
NO
Sheet metal workers
Plenty already — about 893 to spare
NO
Welders
Plenty already — about 2,463 to spare
NO
Plumbers
Plenty already — about 1,912 to spare

"Short" means the data centers need more of that trade at the busiest point than the area has free to take on new work. Most workers stay on their regular jobs; only about 1 in 4 are free for big new projects like these.

Enough workers?

Will Missouri have enough workers?

At the busiest point of the build. Bars to the left mean a shortage (good if you are in that trade). Bars to the right mean workers to spare.

just enough SHORT TO SPARE Ironworkers 39 spare Network/low-voltage technicians 716 spare Sheet metal workers 893 spare Pipefitters 1,828 spare Plumbers 1,912 spare HVAC/R technicians 2,006 spare Welders 2,463 spare Electricians 2,787 spare Carpenters 3,867 spare
The short version

What this means for workers near Kansas City (Northland)

Kansas City (Northland), MO has about 700 MW of AI data centers across 2 sites, with 700 MW still to build. The builders here include Meta, Google.

At the busiest point, about 1,344 skilled workers will be on these sites at once, across all the trades. Many drive in from nearby towns, but the work starts here — and it is not split evenly, so some trades are short and some are not.

Worth training up for? Around Kansas City (Northland), the data centers look most short on ironworkers. Here is the read by trade.

Ironworkers — worth training up: YES, tight. The data centers need about 189 ironworkers at the busiest point — close to all of the ~228 ironworkers Missouri has free for this kind of work. Expect overtime, steady work, and builders willing to train.

Electricians — probably not, just for this. The data centers need about 378 electricians, and Missouri already has about 3,165 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

Network/low-voltage technicians — probably not, just for this. The data centers need about 84 network/low-voltage technicians, and Missouri already has about 800 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

Pipefitters — probably not, just for this. The data centers need about 147 pipefitters, and Missouri already has about 1,975 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

Carpenters — probably not, just for this. The data centers need about 231 carpenters, and Missouri already has about 4,098 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

HVAC/R technicians — probably not, just for this. The data centers need about 84 hvac/r technicians, and Missouri already has about 2,090 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

These are some of the best-paying jobs you can get without a four-year degree. When a trade is short, builders run overtime and pay to train, and experienced workers can clear $100,000 a year, with health care and a pension through the union. It is the same across the country: builders cannot find enough skilled workers. The U.S. needs about 140,000 more trade workers by 2030 to build all the data centers, and most builders say hiring is their hardest problem. Microsoft's president has called the shortage of electricians the biggest thing slowing data centers down.

You sign up and get your license through Missouri. The Missouri trade pages show you how to start. Sources: a national survey of data-center building plans, plus U.S. jobs and pay data.

Every trade

Every trade, by the numbers

Is there a shortage of each trade for the data centers in the Kansas City (Northland) area?
Trade Needed at peak Free to take it on Short or extra New data-center jobs Train up?
Electricians 378 3,165 2,787 spare 26 NO
Carpenters 231 4,098 3,867 spare NO
Ironworkers 189 228 39 spare YES
Pipefitters 147 1,975 1,828 spare NO
Welders 105 2,568 2,463 spare NO
HVAC/R technicians 84 2,090 2,006 spare 12 NO
Network/low-voltage technicians 84 800 716 spare 6 NO
Plumbers 63 1,975 1,912 spare NO
Data center technicians 262 159 spare 103 CLOSE
Sheet metal workers 42 935 893 spare NO
Elevator mechanics 21

"Needed at peak" is the most of that trade working across all the building at the busiest time. "Free to take it on" is how many local workers could move to data-center jobs — about 1 in 4 of the trade; the rest keep their regular jobs. "Short or extra" is the gap. "New data-center jobs" are permanent jobs that stay once a data center opens. "Train up?" is YES when the work needs more than the area can spare (so they pay well and pay to train), NO when there are plenty already. Elevator mechanics are left out of the verdict because their work depends on the building's design.