Boyce is building
data centers

Boyce has 300 MW of data centers across 1 sites. That is a lot of work for the trades, and there are not enough workers nearby to do it.

1 sites |300 MW still to build |576 workers at peak
Running now
0 MW
Still to build
300 MW
Total workers on site at peak
576
Building sites
1
Boyce data centers: running now vs. still to build
Running now: 0 MW Still to build: 300 MW Total: 300 MW
The bottom line

Worth training up for in Louisiana?

YES means the data centers will need more of that trade than Louisiana can spare — so they pay well, pay to train, and run overtime. NO means there are already plenty.

NO
Ironworkers
Plenty already — about 309 to spare
NO
Data center technicians
Enough already — 44 steady jobs once they open
NO
Sheet metal workers
Plenty already — about 202 to spare
NO
Electricians
Plenty already — about 2,540 to spare
NO
Network/low-voltage technicians
Plenty already — about 709 to spare
NO
Carpenters
Plenty already — about 2,106 to spare
NO
Pipefitters
Plenty already — about 2,197 to spare
NO
HVAC/R technicians
Plenty already — about 1,224 to spare
NO
Plumbers
Plenty already — about 2,233 to spare
NO
Welders
Plenty already — about 3,045 to spare

"Short" means the data centers need more of that trade at the busiest point than the area has free to take on new work. Most workers stay on their regular jobs; only about 1 in 4 are free for big new projects like these.

Enough workers?

Will Louisiana have enough workers?

At the busiest point of the build. Bars to the left mean a shortage (good if you are in that trade). Bars to the right mean workers to spare.

just enough SHORT TO SPARE Sheet metal workers 202 spare Ironworkers 309 spare Network/low-voltage technicians 709 spare HVAC/R technicians 1,224 spare Carpenters 2,106 spare Pipefitters 2,197 spare Plumbers 2,233 spare Electricians 2,540 spare Welders 3,045 spare
The short version

What this means for workers near Boyce

Boyce, LA has about 300 MW of AI data centers across 1 site, with 300 MW still to build. The builders here include Applied Digital.

At the busiest point, about 576 skilled workers will be on these sites at once, across all the trades. Many drive in from nearby towns, but the work starts here — and it is not split evenly, so some trades are short and some are not.

Worth training up for? The work near Boyce is steady, but the area has enough workers for most trades. Here is the read by trade.

Ironworkers — probably not, just for this. The data centers need about 81 ironworkers, and Louisiana already has about 390 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

Sheet metal workers — probably not, just for this. The data centers need about 18 sheet metal workers, and Louisiana already has about 220 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

Electricians — probably not, just for this. The data centers need about 162 electricians, and Louisiana already has about 2,702 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

Network/low-voltage technicians — probably not, just for this. The data centers need about 36 network/low-voltage technicians, and Louisiana already has about 745 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

Carpenters — probably not, just for this. The data centers need about 99 carpenters, and Louisiana already has about 2,205 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

Pipefitters — probably not, just for this. The data centers need about 63 pipefitters, and Louisiana already has about 2,260 free for this kind of work. Plenty. Still steady work, but no special data-center shortage.

These are some of the best-paying jobs you can get without a four-year degree. When a trade is short, builders run overtime and pay to train, and experienced workers can clear $100,000 a year, with health care and a pension through the union. It is the same across the country: builders cannot find enough skilled workers. The U.S. needs about 140,000 more trade workers by 2030 to build all the data centers, and most builders say hiring is their hardest problem. Microsoft's president has called the shortage of electricians the biggest thing slowing data centers down.

You sign up and get your license through Louisiana. The Louisiana trade pages show you how to start. Sources: a national survey of data-center building plans, plus U.S. jobs and pay data.

Every trade

Every trade, by the numbers

Is there a shortage of each trade for the data centers in the Boyce area?
Trade Needed at peak Free to take it on Short or extra New data-center jobs Train up?
Electricians 162 2,702 2,540 spare 11 NO
Carpenters 99 2,205 2,106 spare NO
Ironworkers 81 390 309 spare NO
Pipefitters 63 2,260 2,197 spare NO
Welders 45 3,090 3,045 spare NO
HVAC/R technicians 36 1,260 1,224 spare 5 NO
Network/low-voltage technicians 36 745 709 spare 3 NO
Plumbers 27 2,260 2,233 spare NO
Data center technicians 258 214 spare 44 NO
Sheet metal workers 18 220 202 spare NO
Elevator mechanics 9

"Needed at peak" is the most of that trade working across all the building at the busiest time. "Free to take it on" is how many local workers could move to data-center jobs — about 1 in 4 of the trade; the rest keep their regular jobs. "Short or extra" is the gap. "New data-center jobs" are permanent jobs that stay once a data center opens. "Train up?" is YES when the work needs more than the area can spare (so they pay well and pay to train), NO when there are plenty already. Elevator mechanics are left out of the verdict because their work depends on the building's design.